Log Home Construction - Miscellaneous Rough Interior


Installing Loft Floor, Partitions, Wiring - September 19 - 25, 2003

September 19, 2003 - Loft floor and wiring

loft_9-19-03_floor1.jpg (63341 bytes) loft_9-19-03_floor2.jpg (66906 bytes) loft_9-19-03_floor3.jpg (65441 bytes) loft_9-19-03_floor4.jpg (54333 bytes) loft_9-19-03_floor5.jpg (61263 bytes) wiring_9-19-03_2nd_floor_receptacle.jpg (46641 bytes) wiring_9-19-03_2nd_floor_joist_bottom1.jpg (51844 bytes) wiring_9-19-03_2nd_floor_joist_top1.jpg (65038 bytes) wiring_9-19-03_2nd_floor_joist_top2.jpg (52637 bytes) wiring_9-19-03_2nd_floor_joist_top3.jpg (46499 bytes) wiring_9-19-03_2nd_floor_joist_bottom2.jpg (54548 bytes)

September 22, 2003 - Finished loft floor, started partitions, set 6x6 posts

loft_9-22-03_2nd_floor_finished.jpg (49236 bytes) loft_9-22-03_2nd_floor_framing.jpg (64577 bytes) loft_9-22-03_2nd_floor_6x6_posts1.jpg (63128 bytes) loft_9-22-03_2nd_floor_6x6_posts2.jpg (53360 bytes)

September 25, 2003 - Finished first and second floor partitions

framing_9-25-03_1st_floor.jpg (62561 bytes) framing_9-25-03_2nd_floor1.jpg (57532 bytes) framing_9-25-03_2nd_floor2.jpg (70454 bytes) framing_9-25-03_2nd_floor_closeup.jpg (57625 bytes)

Painting Metal Brackets - September 27 - 28, 2003

September 27, 2003 - Sanding and priming metal brackets (January 25, 2004 note: The black bedliner paint below tended to peel off of the primer. We ran short on metal brackets and had to order more from Jim Barna. We did not use primer on the second batch. The bedliner paint adhered to the metal and resulted in a much nicer finish which did not peel off when the brackets were installed.)

metal_9-27-03_before_grinding.jpg (79082 bytes) metal_9-27-03_before_and_after_grinding.jpg (71743 bytes) metal_9-27-03_sanding_with_steel_wool1.jpg (62927 bytes) metal_9-27-03_sanding_with_steel_wool2.jpg (58237 bytes) metal_9-27-03_painted_with_primer.jpg (51394 bytes)

September 28, 2003 - Painted with PlastiKoat bedliner for "iron skillet" look

metal_9-28-03_painted_with_bedliner.jpg (48490 bytes) metal_9-28-03_painted_with_bedliner_closeup2.jpg (60978 bytes) metal_9-28-03_painted_with_bedliner_closeup1.jpg (121170 bytes)

Roughing In Plumbing - October 6 - 8, 2003

October 6, 2003

plumbing_10-6-03_day1_2nd_floor_underneath1.jpg (56705 bytes) plumbing_10-6-03_day1_2nd_floor_underneath2.jpg (50502 bytes) plumbing_10-6-03_day1_2nd_floor_toilet_and_sink.jpg (51064 bytes)

October 7, 2003

The first photo below shows a coil of flexible copper in the subfloor. As the second floor settles and pushes the water lines downward, the coil will absorb the settling to prevent damage to the lines. The water lines and conduit fit nicely through the floor trusses.

plumbing_10-7-03_day2_settling_allowance_in_subfloor.jpg (61325 bytes) plumbing_10-7-03_day2_floor_joists3.jpg (66989 bytes) plumbing_10-7-03_day2_floor_joists1.jpg (62551 bytes) plumbing_10-7-03_day2_laundry_underneath.jpg (51327 bytes) plumbing_10-7-03_day2_floor_joists2.jpg (61142 bytes) plumbing_10-7-03_day2_kitchen_underneath.jpg (53259 bytes) plumbing_10-7-03_day2_showers_delivered.jpg (52765 bytes) plumbing_10-7-03_day2_laundry_room.jpg (43858 bytes)

October 8, 2003

plumbing_10-8-03_day3_2nd_floor1.jpg (55043 bytes) plumbing_10-8-03_day3_2nd_floor2.jpg (57376 bytes) plumbing_10-8-03_day3_1st_floor.jpg (58120 bytes) plumbing_10-8-03_day3_roof_vent.jpg (54713 bytes) plumbing_10-8-03_day3_master_shower.jpg (43284 bytes) plumbing_10-8-03_day3_2nd_shower1.jpg (49477 bytes) plumbing_10-8-03_day3_2nd_shower2.jpg (51599 bytes)

More Wiring - October 14 - 17, 2003

October 14, 2003

wiring_10-14-03_breaker_box.jpg (51805 bytes) wiring_10-14-03_bedroom_switch.jpg (45055 bytes) wiring_10-14-03_bottom_stairs_switch.jpg (53981 bytes) wiring_10-14-03_top_stairs_switch.jpg (66252 bytes)

October 15, 2003

wiring_10-15-03_foyer_ceiling.jpg (53136 bytes) wiring_10-15-03_kitchen_ceiling.jpg (50265 bytes) wiring_10-15-03_shed_dormer.jpg (63992 bytes) wiring_10-15-03_log_receptacle_hole1.jpg (37861 bytes) wiring_10-15-03_log_receptacle_hole2.jpg (43937 bytes) wiring_10-15-03_in_roof_sandwich.jpg (37397 bytes) wiring_10-15-03_2nd_bedroom1.jpg (68187 bytes) wiring_10-15-03_2nd_bedroom2.jpg (63340 bytes) wiring_10-15-03_loft.jpg (61271 bytes) wiring_10-15-03_shed_dormer_bathroom.jpg (74051 bytes) wiring_10-15-03_shed_dormer_loft.jpg (78273 bytes)

October 17, 2003

wiring_10-17-03_receptacle_box.jpg (52360 bytes) wiring_10-17-03_dining_room_switches.jpg (51549 bytes)

More Plumbing - October 20, 2003

plumbing_10-20-03_day4_master_shower_pipes1.jpg (53753 bytes) plumbing_10-20-03_day4_master_shower_faucet.jpg (26178 bytes) plumbing_10-20-03_day4_venetion_bronze.jpg (18298 bytes) plumbing_10-20-03_day4_water_line.jpg (95609 bytes)

Installing Windows and Doors - October 27, 2003

windows_10-27-03_front1.jpg (71116 bytes) windows_10-27-03_front2.jpg (67618 bytes) windows_10-27-03_front_yard.jpg (81466 bytes) windows_10-27-03_front_yard_angle.jpg (90169 bytes) windows_10-27-03_knoll_angle.jpg (74287 bytes) windows_10-27-03_back.jpg (75653 bytes) windows_10-27-03_inside_back_door.jpg (58958 bytes) windows_10-27-03_inside_kitchen.jpg (54491 bytes) windows_10-27-03_master_bath.jpg (54877 bytes)

Preparing and Pouring Basement Floor - October 30 - 31, 2003

Preparing Ground - October 30, 2003

slab_10-30-03_prepared_for_pouring1.jpg (64072 bytes) slab_10-30-03_prepared_for_pouring3.jpg (66146 bytes) slab_10-30-03_prepared_for_pouring2.jpg (58783 bytes) slab_10-30-03_wire_mesh.jpg (87066 bytes)

Finished Floor - October 31, 2003

slab_10-31-03_poured1.jpg (53988 bytes) slab_10-31-03_poured2.jpg (53920 bytes) slab_10-31-03_poured3.jpg (45981 bytes)

Installing Basement Partitions and Stairs - November 5 - 6, 2003

framing_11-5-03_basement1.jpg (73814 bytes) framing_11-5-03_basement2.jpg (74276 bytes) framing_11-5-03_basement3.jpg (45257 bytes) framing_11-6-03_basement_stairs.jpg (69530 bytes)

Installing Network and Phone Cable - November 8, 2003

network_cable_11-8-03_basement.jpg (48719 bytes) network_cable_11-8-03_thru_chase.jpg (56401 bytes) network_cable_11-8-03_2nd_bedroom.jpg (56274 bytes)

Installing Insulation in Second Floor Shed Dormer - November 9, 2003

insulation_11-9-03_awaiting_us.jpg (58770 bytes) insulation_11-9_03_shed_dormer2.jpg (72135 bytes) insulation_11-9-03_shed_dormer1.jpg (50346 bytes)

More Plumbing - November 15, 2003

plumbing_11-15-03_ritchie_in_basement.jpg (69797 bytes)

Installing HVAC - October 28 - December 10, 2003

All HVAC materials were delivered on October 28, 2003. We met with the installers on October 30 to discuss register and cold air return locations. Register holes were cut out on November 5. The furnace was set, the main trunk line was started, and the metal "openings" were installed below all register holes on November 14.

hvac_11-14-03_furnace_installed.jpg (52721 bytes)

Running Ducts in Basement - November 17, 2003

hvac_11-17-03_basement1.jpg (79797 bytes) hvac_11-17-03_basement2.jpg (82114 bytes) hvac_11-17-03_basement3.jpg (72724 bytes) hvac_11-17-03_basement_register.jpg (67153 bytes)

Finishing Window Installation - November 26 and 28, 2003

The custom glass above the kitchen window and the triangles in the foyer took awhile to be made, but they were finally received and were installed around Thanksgiving.

windows_11-26-03_adding_t-jambs_to_traps1.jpg (57022 bytes) windows_11-26-03_adding_t-jambs_to_traps2.jpg (50605 bytes) windows_11-26-03_traps_complete2.jpg (71891 bytes) windows_11-26-03_traps_complete1.jpg (67725 bytes) windows_11-28-03_triangles_in_foyer.jpg (64387 bytes)

Insulating Around Windows - December 7, 2003

insulation_12-07-03_front_foyer_windows.jpg (60443 bytes)

More Plumbing - Hot Water Heater Installed December 22, 2003

plumbing_12-22-03_hot_water_tank.jpg (49538 bytes)


 