          1 2

Confirmed location of gas line.

3

Cleaned moldy purlins with bleach and power sprayer. Purlins are permanently stained. Took pictures.

4

Dug trench for power cable. Installed string and conduit. Ordered floor trusses. Health dept. site visit to discuss septic.
(PHOTOS)

5

Connected meter base, breaker box, and wiring to pole for temp power. Sent purlin pictures to Barna, who agreed to replace them.

6

Septic installer site visit to discuss septic options.

7

Installed plumbing in basement floor.
(PHOTOS)

8 9

Set temporary power pole and grounding rod in trench.
(PHOTOS)

10 11

Delivered floor trusses.
(PHOTOS)

12

Set floor trusses. Delivered rest of sub-floor materials.
(PHOTOS)

13

Completed half of sub-floor. Power company connected temporary power.
(PHOTOS)

14

Completed sub-floor. BEGAN SETTING LOGS.
(PHOTOS)

15

Continued setting logs.
(PHOTOS)

16

Obtained window and door estimate.

17 18

Continued setting logs.
(PHOTOS)

19

Continued setting logs. Obtained another window and door estimate.
(PHOTOS)

20

Continued setting logs.
(PHOTOS)

21

Continued setting logs.
(PHOTOS)

22

Continued setting logs.
(PHOTOS)

23
24 25

Finished setting logs to top of first floor.

26

Started setting beams for second floor.
(PHOTOS)

27

Started framing first floor wall partitions.
(PHOTOS)

28

Set logs for gable end over bedrooms, some above garage. Placed window and door order.
(PHOTOS)

29

Continued setting gable logs over garage and foyer. Started constructing wall for shed dormer.
(PHOTOS)

30
31            
 